Critical Factors and Mitigating Measures of Construction Delays of Pakistani Building Construction Projects
The construction industry is a significant contributor to a country's Gross Domestic Product (GDP). However, construction projects often face many issues especially delay. It is a key contributor to project failure, leading to cost overruns and a decline in quality standards. This study aims to...
Saved in:
Main Authors: | , , , |
---|---|
Format: | Article |
Language: | English |
Published: |
uthm
2023
|
Subjects: | |
Online Access: | http://eprints.uthm.edu.my/9525/1/J16031_967153c8453a3abe1e8fa22bd83b29f9.pdf http://eprints.uthm.edu.my/9525/ https://doi.org/10,30880/ij |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
id |
my.uthm.eprints.9525 |
---|---|
record_format |
eprints |
spelling |
my.uthm.eprints.95252023-08-02T03:45:16Z http://eprints.uthm.edu.my/9525/ Critical Factors and Mitigating Measures of Construction Delays of Pakistani Building Construction Projects Irfanullah, Irfanullah Hasmoril, Muhammad Fikri Hassan Memon, Mujtaba Ismail, Radzi T Technology (General) The construction industry is a significant contributor to a country's Gross Domestic Product (GDP). However, construction projects often face many issues especially delay. It is a key contributor to project failure, leading to cost overruns and a decline in quality standards. This study aims to identify the critical factors of delay in building construction projects in Pakistan, and its controlling measures of the critical delay factors. A literature review identified 48 common factors of delay in the construction industry worldwide. Based on a structured questionnaire and the average index method, 11 critical factors of delays in building construction projects in Pakistan were identified. Furthermore, a semi-structured questionnaire was used to determine 44 possible mitigation measures which were extracted from literature review with the 11 critical delay factors. The results of this study will be useful for stakeholders in building construction projects in Pakistan. By incorporating the recommended mitigation measures, they can identify and control the most critical factors that can cause delays in building construction projects. This study contributes to the existing literature by providing a better understanding of the factors causing delays in building construction projects in Pakistan and proposing effective measures to mitigate these factors. uthm 2023 Article PeerReviewed text en http://eprints.uthm.edu.my/9525/1/J16031_967153c8453a3abe1e8fa22bd83b29f9.pdf Irfanullah, Irfanullah and Hasmoril, Muhammad Fikri and Hassan Memon, Mujtaba and Ismail, Radzi (2023) Critical Factors and Mitigating Measures of Construction Delays of Pakistani Building Construction Projects. LNTERNATIONAL JOURNAL OF SUSTAINABLE CONSTRUCTION ENGINEERING AND TECHNOLOGY, 14 (2). pp. 240-249. ISSN 2600-7959 https://doi.org/10,30880/ij |
institution |
Universiti Tun Hussein Onn Malaysia |
building |
UTHM Library |
collection |
Institutional Repository |
continent |
Asia |
country |
Malaysia |
content_provider |
Universiti Tun Hussein Onn Malaysia |
content_source |
UTHM Institutional Repository |
url_provider |
http://eprints.uthm.edu.my/ |
language |
English |
topic |
T Technology (General) |
spellingShingle |
T Technology (General) Irfanullah, Irfanullah Hasmoril, Muhammad Fikri Hassan Memon, Mujtaba Ismail, Radzi Critical Factors and Mitigating Measures of Construction Delays of Pakistani Building Construction Projects |
description |
The construction industry is a significant contributor to a country's Gross Domestic Product (GDP). However, construction projects often face many issues especially delay. It is a key contributor to project failure, leading to cost overruns and a decline in quality standards. This study aims to identify the critical factors of delay in building construction projects in Pakistan, and its controlling measures of the critical delay factors. A literature review identified 48 common factors of delay in the construction industry worldwide. Based on a structured questionnaire and the average index method, 11 critical factors of delays in building construction projects in Pakistan were identified. Furthermore, a semi-structured questionnaire was used to determine 44 possible mitigation measures which were extracted from literature review with the 11 critical delay factors. The results of this study will be useful for stakeholders in building construction projects in Pakistan. By incorporating the recommended mitigation measures, they can identify and control the most critical factors that can cause delays in building construction projects. This study contributes to the existing literature by providing a better understanding of the factors causing delays in building construction projects in Pakistan and proposing effective measures to mitigate these factors. |
format |
Article |
author |
Irfanullah, Irfanullah Hasmoril, Muhammad Fikri Hassan Memon, Mujtaba Ismail, Radzi |
author_facet |
Irfanullah, Irfanullah Hasmoril, Muhammad Fikri Hassan Memon, Mujtaba Ismail, Radzi |
author_sort |
Irfanullah, Irfanullah |
title |
Critical Factors and Mitigating Measures of Construction Delays of Pakistani Building Construction Projects |
title_short |
Critical Factors and Mitigating Measures of Construction Delays of Pakistani Building Construction Projects |
title_full |
Critical Factors and Mitigating Measures of Construction Delays of Pakistani Building Construction Projects |
title_fullStr |
Critical Factors and Mitigating Measures of Construction Delays of Pakistani Building Construction Projects |
title_full_unstemmed |
Critical Factors and Mitigating Measures of Construction Delays of Pakistani Building Construction Projects |
title_sort |
critical factors and mitigating measures of construction delays of pakistani building construction projects |
publisher |
uthm |
publishDate |
2023 |
url |
http://eprints.uthm.edu.my/9525/1/J16031_967153c8453a3abe1e8fa22bd83b29f9.pdf http://eprints.uthm.edu.my/9525/ https://doi.org/10,30880/ij |
_version_ |
1773545912655675392 |
score |
13.211869 |