Factors influencing the construction time of public sector civil engineering projects in Malaysia / Ahmad Anuar Othman
The government appears to be the major provider of infrastructure projects in many developing countries including Malaysia. There are limitations and even drawbacks to these efforts as time required to complete the construction of public projects is frequently greater than the time originally specif...
Saved in:
Main Author: | |
---|---|
Format: | Thesis |
Language: | English |
Published: |
2006
|
Subjects: | |
Online Access: | https://ir.uitm.edu.my/id/eprint/42473/1/42473.pdf https://ir.uitm.edu.my/id/eprint/42473/ |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
id |
my.uitm.ir.42473 |
---|---|
record_format |
eprints |
spelling |
my.uitm.ir.424732023-08-18T05:18:03Z https://ir.uitm.edu.my/id/eprint/42473/ Factors influencing the construction time of public sector civil engineering projects in Malaysia / Ahmad Anuar Othman Othman, Ahmad Anuar Engineering instruments, meters, etc. Industrial instrumentation The government appears to be the major provider of infrastructure projects in many developing countries including Malaysia. There are limitations and even drawbacks to these efforts as time required to complete the construction of public projects is frequently greater than the time originally specified in the contract. The main purpose of the study is to identify factors affecting the construction time of public sector civil engineering projects in Malaysia. The study had been structured into three different phases where each phase" had specific objectives and adopted different methods of data collection and analyses. The first phase was based on 244 data sets collected from project files from three different public agencies completed between 1999 and 2003. Irrigation and flood mitigation, roads and sewerage projects were found to be delayed on average 26, 37 and 4 percent of their original contract duration respectively. Multiple regression analysis indicated that construction time performance of public projects was affected more by excusable variables than project characteristics variables. Through the regression models different variables were found to have different levels of effect on the construction time performance. The second phase adopted a mailed questionnaire survey involving three groups of respondents, namely, government engineers, consultants and contractors. Out of 413 questionnaires mailed, 249 (60.3%) were duly returned. Using factor analysis and logistic regression, five factors with 42 underlying variables were found to be significant in contributing to the probability of project delays. The third or final phase adopted case studies involving ten selected projects, five completed early or on time while the other five experienced delay in completion time. A total of 20 persons were interviewed involving both contractors and superintending officers' staff. The results of the case studies validated the findings of the earlier phases. The study concluded that the construction time of public projects can be affected by a number of factors, they were contractor and workers related factor, project or site related factor, contractor's financial status, superintending officer and contractual relationships, and materials related factors. Recommendations were put forward at the end of the study to improve the construction time and minimize delays in public projects. 2006 Thesis NonPeerReviewed text en https://ir.uitm.edu.my/id/eprint/42473/1/42473.pdf Factors influencing the construction time of public sector civil engineering projects in Malaysia / Ahmad Anuar Othman. (2006) PhD thesis, thesis, Universiti Teknologi MARA (UiTM). |
institution |
Universiti Teknologi Mara |
building |
Tun Abdul Razak Library |
collection |
Institutional Repository |
continent |
Asia |
country |
Malaysia |
content_provider |
Universiti Teknologi Mara |
content_source |
UiTM Institutional Repository |
url_provider |
http://ir.uitm.edu.my/ |
language |
English |
topic |
Engineering instruments, meters, etc. Industrial instrumentation |
spellingShingle |
Engineering instruments, meters, etc. Industrial instrumentation Othman, Ahmad Anuar Factors influencing the construction time of public sector civil engineering projects in Malaysia / Ahmad Anuar Othman |
description |
The government appears to be the major provider of infrastructure projects in many developing countries including Malaysia. There are limitations and even drawbacks to these efforts as time required to complete the construction of public projects is frequently greater than the time originally specified in the contract. The main purpose of the study is to identify factors affecting the construction time of public sector civil engineering projects in Malaysia. The study had been structured into three different phases where each phase" had specific objectives and adopted different methods of data collection and analyses. The first phase was based on 244 data sets collected from project files from three different public agencies completed between 1999 and 2003. Irrigation and flood mitigation, roads and sewerage projects were found to be delayed on average 26, 37 and 4 percent of their original contract duration respectively. Multiple regression analysis indicated that construction time performance of public projects was affected more by excusable variables than project characteristics variables. Through the regression models different variables were found to have different levels of effect on the construction time performance. The second phase adopted a mailed questionnaire survey involving three groups of respondents, namely, government engineers, consultants and contractors. Out of 413 questionnaires mailed, 249 (60.3%) were duly returned. Using factor analysis and logistic regression, five factors with 42 underlying variables were found to be significant in contributing to the probability of project delays. The third or final phase adopted case studies involving ten selected projects, five completed early or on time while the other five experienced delay in completion time. A total of 20 persons were interviewed involving both contractors and superintending officers' staff. The results of the case studies validated the findings of the earlier phases. The study concluded that the construction time of public projects can be affected by a number of factors, they were contractor and workers related factor, project or site related factor, contractor's financial status, superintending officer and contractual relationships, and materials related factors. Recommendations were put forward at the end of the study to improve the construction time and minimize delays in public projects. |
format |
Thesis |
author |
Othman, Ahmad Anuar |
author_facet |
Othman, Ahmad Anuar |
author_sort |
Othman, Ahmad Anuar |
title |
Factors influencing the construction time of public sector civil engineering projects in Malaysia / Ahmad Anuar Othman |
title_short |
Factors influencing the construction time of public sector civil engineering projects in Malaysia / Ahmad Anuar Othman |
title_full |
Factors influencing the construction time of public sector civil engineering projects in Malaysia / Ahmad Anuar Othman |
title_fullStr |
Factors influencing the construction time of public sector civil engineering projects in Malaysia / Ahmad Anuar Othman |
title_full_unstemmed |
Factors influencing the construction time of public sector civil engineering projects in Malaysia / Ahmad Anuar Othman |
title_sort |
factors influencing the construction time of public sector civil engineering projects in malaysia / ahmad anuar othman |
publishDate |
2006 |
url |
https://ir.uitm.edu.my/id/eprint/42473/1/42473.pdf https://ir.uitm.edu.my/id/eprint/42473/ |
_version_ |
1775626318338064384 |
score |
13.211869 |