Mitigating Delay Impacts in Construction Projects: An Evaluation of Causes and Strategies
Construction plays a crucial role in driving national economic growth for sustainable development. Nonetheless, delays in many building projects emerged due to various challenges. Identifying and addressing these delays proved essential for ensuring project success. Timely completion stood as a k...
Saved in:
Main Authors: | , , , , , |
---|---|
Format: | Article |
Language: | English English |
Published: |
INTI International University
2024
|
Subjects: | |
Online Access: | http://eprints.intimal.edu.my/2096/1/ij2024_49.pdf http://eprints.intimal.edu.my/2096/2/635 http://eprints.intimal.edu.my/2096/ https://intijournal.intimal.edu.my |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
id |
my-inti-eprints.2096 |
---|---|
record_format |
eprints |
spelling |
my-inti-eprints.20962024-12-24T05:19:35Z http://eprints.intimal.edu.my/2096/ Mitigating Delay Impacts in Construction Projects: An Evaluation of Causes and Strategies Ijaz, Ahmad Syed, Saad Syed Nouman, Shah Muhammad, Bilal Fabiha Fatima, Agha Sumayya, Obaid T Technology (General) TA Engineering (General). Civil engineering (General) TC Hydraulic engineering. Ocean engineering TH Building construction Construction plays a crucial role in driving national economic growth for sustainable development. Nonetheless, delays in many building projects emerged due to various challenges. Identifying and addressing these delays proved essential for ensuring project success. Timely completion stood as a key indicator of project success, whereas delays could result in increased costs and disputes among stakeholders. This study aimed to explore the causes of delays in construction projects and their remedial measures. Specifically, the research investigated delay factors in construction projects across Khyber Pakhtunkhwa, including the Machai Hydro Power Project in Mardan, the Golen Gol Hydro Power Project in Chitral, the KOTO Hydro Power Project in Lower Dir, and the rehabilitation of the Peshawar to Dara Adam Khel carriageway. Data was collected through Google Forms, with participants providing valuable responses. The analysis was conducted using IBM SPSS. Results indicated that land acquisition, client issues, consultant problems, general factors, and budget conflicts had the most significant impact on delays. This study offered important insights into the construction industry, highlighting strategies to mitigate these issues and improve project efficiency. INTI International University 2024-12 Article PeerReviewed text en cc_by_4 http://eprints.intimal.edu.my/2096/1/ij2024_49.pdf text en cc_by_4 http://eprints.intimal.edu.my/2096/2/635 Ijaz, Ahmad and Syed, Saad and Syed Nouman, Shah and Muhammad, Bilal and Fabiha Fatima, Agha and Sumayya, Obaid (2024) Mitigating Delay Impacts in Construction Projects: An Evaluation of Causes and Strategies. INTI JOURNAL, 2024 (49). pp. 1-7. ISSN e2600-7320 https://intijournal.intimal.edu.my |
institution |
INTI International University |
building |
INTI Library |
collection |
Institutional Repository |
continent |
Asia |
country |
Malaysia |
content_provider |
INTI International University |
content_source |
INTI Institutional Repository |
url_provider |
http://eprints.intimal.edu.my |
language |
English English |
topic |
T Technology (General) TA Engineering (General). Civil engineering (General) TC Hydraulic engineering. Ocean engineering TH Building construction |
spellingShingle |
T Technology (General) TA Engineering (General). Civil engineering (General) TC Hydraulic engineering. Ocean engineering TH Building construction Ijaz, Ahmad Syed, Saad Syed Nouman, Shah Muhammad, Bilal Fabiha Fatima, Agha Sumayya, Obaid Mitigating Delay Impacts in Construction Projects: An Evaluation of Causes and Strategies |
description |
Construction plays a crucial role in driving national economic growth for sustainable development.
Nonetheless, delays in many building projects emerged due to various challenges. Identifying and
addressing these delays proved essential for ensuring project success. Timely completion stood as
a key indicator of project success, whereas delays could result in increased costs and disputes
among stakeholders. This study aimed to explore the causes of delays in construction projects and
their remedial measures. Specifically, the research investigated delay factors in construction
projects across Khyber Pakhtunkhwa, including the Machai Hydro Power Project in Mardan, the
Golen Gol Hydro Power Project in Chitral, the KOTO Hydro Power Project in Lower Dir, and the
rehabilitation of the Peshawar to Dara Adam Khel carriageway. Data was collected through
Google Forms, with participants providing valuable responses. The analysis was conducted using
IBM SPSS. Results indicated that land acquisition, client issues, consultant problems, general
factors, and budget conflicts had the most significant impact on delays. This study offered
important insights into the construction industry, highlighting strategies to mitigate these issues
and improve project efficiency. |
format |
Article |
author |
Ijaz, Ahmad Syed, Saad Syed Nouman, Shah Muhammad, Bilal Fabiha Fatima, Agha Sumayya, Obaid |
author_facet |
Ijaz, Ahmad Syed, Saad Syed Nouman, Shah Muhammad, Bilal Fabiha Fatima, Agha Sumayya, Obaid |
author_sort |
Ijaz, Ahmad |
title |
Mitigating Delay Impacts in Construction Projects: An Evaluation of Causes and Strategies |
title_short |
Mitigating Delay Impacts in Construction Projects: An Evaluation of Causes and Strategies |
title_full |
Mitigating Delay Impacts in Construction Projects: An Evaluation of Causes and Strategies |
title_fullStr |
Mitigating Delay Impacts in Construction Projects: An Evaluation of Causes and Strategies |
title_full_unstemmed |
Mitigating Delay Impacts in Construction Projects: An Evaluation of Causes and Strategies |
title_sort |
mitigating delay impacts in construction projects: an evaluation of causes and strategies |
publisher |
INTI International University |
publishDate |
2024 |
url |
http://eprints.intimal.edu.my/2096/1/ij2024_49.pdf http://eprints.intimal.edu.my/2096/2/635 http://eprints.intimal.edu.my/2096/ https://intijournal.intimal.edu.my |
_version_ |
1819915648267976704 |
score |
13.223943 |