Systematic approach for developing as-built schedule for construction project
It is widely recognized that construction industry is information intensive and complex industry. However, present trend and proliferations towards multi-participant mega projects have heightened the need for an effective and efficient evaluation and monitoring by stakeholders. A persistent proble...
Saved in:
Main Authors: | , , , |
---|---|
Format: | Article |
Language: | English |
Published: |
2006
|
Online Access: | http://journalarticle.ukm.my/1455/1/2006-14.pdf http://journalarticle.ukm.my/1455/ http://www.ukm.my/jkukm/index.php/jkukm |
Tags: |
Add Tag
No Tags, Be the first to tag this record!
|
Summary: | It is widely recognized that construction industry is information intensive and complex industry. However,
present trend and proliferations towards multi-participant mega projects have heightened the need for an
effective and efficient evaluation and monitoring by stakeholders. A persistent problem in construction has
been in documenting changes, which occur in the field, and preparing the as-built schedule. Combining
computer vision technology with 3D CAD to produce as-built drawing offers a potential solution.
However a recent investigation indicated that there is a lack of systematic and automated evaluation
and monitoring in construction projects. The aim of this research is to identify techniques which are used
in the construction industry for monitoring and evaluating the actual physical progress and to establish
how the current computer technology can be used for monitoring the construction physical progress
on site. 3D CAD is increasingly being used as a design tool for construction projects and digital images
can be used to provide accurate information needed to document as-built construction schedule. The
DCM provides a bridge for storing structural design information in an integrated construction relational
database management system that can be shared by a range of computer applications. The DCM model
is a part of developing the Tele-Construction base site management system, which retrieves the status of
construction work in progress and develop the actual progress bar chart. A pilot study of Car Parking for
Larkin Mosque is conducted to check the validity of DCM. The application of DCM model in monitoring
the progress enables project management teams to better track and controls the productivity and
provides better mechanism for management of project |
---|